In shortOwners: identify facility needs, review capacity and decision authority. Contractors: identify the specified book, requested coefficient categories and requirements for proposals, issuance and closeout.[1][2]

Owners considering a program

  • List the facility needs: identify repair, maintenance, renovation and minor construction work you want to evaluate within the JOC framework.
  • Assign procurement and legal review: ask your responsible advisers what authority and documents are needed before establishing a program.
  • Name the facility contacts: identify who can explain existing conditions, arrange access and confirm the intended result at each site.
  • Assign scope development: choose who records site observations, writes work boundaries and resolves missing details after the meeting.
  • Identify the pricing references: establish which price book and coefficient categories the proposed program documents will use.
  • Assign proposal review: identify who can compare entries with the scope, verify quantity support and check the applicable factor.
  • Define approval and issuance: record who performs each review and who has authority to issue a job order.
  • Prepare the records process: decide where scopes, photographs, takeoffs, proposals, decisions and issued documents will be kept.
  • Plan work decisions: identify how questions, newly observed conditions and requested additions will reach the authorized decision-maker.
  • Set the closeout requirements: identify the completion checks and records needed before a job package is considered finished.
  • Test the handoffs: take a proposed facility need through these assignments and resolve any step with no responsible person.
[1][2]

Contractors evaluating a solicitation

  • Locate the specified book: confirm the exact reference and accompanying pricing instructions before evaluating the requested bid inputs.
  • Check unit-price inclusions: account for direct material, labor and equipment in book prices, with indirect costs and profit outside them.
  • Identify every requested coefficient: contractors bid their factors, so record each category and the instructions that apply to it.
  • Confirm working-hours definitions: distinguish normal from other than normal hours using the solicitation’s language, not an assumed school or facility schedule.
  • Review non-prepriced treatment: identify required support and pricing instructions for work outside the book, which generally carries a factor above 1.00.
  • Examine access requirements: note who arranges entry, what site information is supplied and what working conditions still need clarification.
  • Locate scope and proposal requirements: identify required descriptions, quantity support, attachments and the process for answering review comments.
  • Check order authorization: identify the documents and authorized action required before work may begin.
  • Review contract periods and options: locate any option year provisions and clarify how they affect the solicitation you are evaluating.
  • Locate work and closeout procedures: identify how decisions are recorded and what completion information must be submitted.
  • Submit focused questions: cite the document passage, explain the missing information and use the solicitation’s stated clarification process.
[3][2][4]

Programs vary; check your solicitation and contract for requirements and authority to proceed.

Sources

  1. Cassell and Gilday, "Improving the Army's Job Order Contracting Program" (1997)
  2. Arizona State University, "Job Order Contracting Performance" (2015 report)
  3. Army Federal Acquisition Regulation Supplement (AFARS), "Subpart 5117.90 - Job Order Contracts"
  4. Associated Schools of Construction, "Job-Order-Contracting for Facility Owners" (2006)
Keep exploringThe JOC glossary