In shortDefine the work, document the site meeting, price the scope, resolve review questions and obtain the required job order authorization. Keep the issued scope available during work and closeout.[1][2]

Start with the facility need

Illustrative example: a school district needs to replace damaged ceiling tiles and repaint a corridor over a holiday break. The corridor, intended work and proposed work window are scenario details, not a real project or a pricing benchmark. The following steps carry that same job from scope development to completion.

Write the need as a location and a result: replace the identified damaged tiles and repaint the specified corridor surfaces. Identify the school representative who can confirm the area and arrange access. Bring the contractor and relevant trade participants to the joint scope meeting.

1Identify the need
2Joint scope meeting
3Scope of work
4Contractor proposal
5Owner review
6Job order issued
7Work and closeout

Walk the corridor and define the work

During the walk, identify the damaged tiles rather than assume the entire ceiling needs replacement. Photograph their locations and record the tile details needed to describe the replacement. Measure the surfaces proposed for painting and mark the limits on a sketch.

Ask the school representative to confirm access routes, areas available for staging and which adjacent spaces must stay usable. Record the proposed working dates and hours. A holiday break does not by itself determine whether the work belongs in a normal or other than normal working-hours category.

Write the scope with separate tasks for the ceiling work and the repainting. State what is included, what is excluded and what remains unconfirmed. Attach the labeled photographs and measurement notes so the contractor and reviewer use the same evidence.

  • Ceiling: identify the tiles to replace and the existing grid or adjacent areas to retain.
  • Painting: identify surfaces, preparation and the intended finish.
  • Access: record the agreed entry route and school contact.
  • Schedule: record the proposed work window and exact hours for category review.
  • Open questions: assign each missing detail to a person and a follow-up action.

Build the priced proposal

For each selected price-book line item, multiply unit price by quantity and the applicable contractor coefficient. The book provides the task and unit price; the corridor measurements support the quantity. Keep the scope reference beside each entry so the reviewer can trace its purpose.[1][3][4]

Find entries that represent the described ceiling and painting work, then read their full descriptions and units. Do not assume a tile-replacement entry includes every associated task or that a painting entry covers every preparation step. Check the actual descriptions before adding or omitting work.

Solicitations may distinguish normal from other than normal working hours, and work outside normal hours is generally expected to carry a higher coefficient. Compare the proposed corridor work hours with the solicitation’s definitions. Record the selected category and factor in the proposal.

Resolve specific review questions

Because both parties price from the same book, negotiation is mostly about selected items and quantities. For the corridor, the owner should compare the tile selections and painting entries with the scope before discussing the total. The contractor should provide the takeoff and explain any entry whose purpose is not obvious.[2]

If the reviewer asks whether the adjoining lobby is included, answer the scope question first. If it is excluded, confirm the boundary; if it is added, revise the scope, quantities and affected selections. Do not leave the written description unchanged while pricing a larger area.

If the painting quantity looks wrong, compare the takeoff with the marked surfaces and the selected entry’s unit. If the hours category looks wrong, compare the proposed schedule with its definition. Record each answer and identify the matching scope and proposal revisions.

Issue the order before starting

Identify the authorized issuer and assemble the documents required for the job order. Keep the final corridor scope, priced proposal and review decisions together. Tell the people carrying out the work which version was issued; do not rely on an earlier site note.

During the work, record any newly identified condition against the affected task and location. If more damaged tiles are found outside the described area, document them and seek the required decision before treating them as part of the ordered work. Preserve both the original boundary and any authorized revision.

Close out against the issued scope

Walk the corridor against the issued description: check the identified tile replacement and specified painted surfaces. List incomplete tasks and assign the next action. Assemble the completion records required by the contract.

File the final scope, proposal, issuance records, decisions and closeout documents as one job package. Keep location labels consistent throughout. The record should let another reviewer connect the work completed with the work that was ordered.

Programs vary; check your solicitation and contract for requirements and authority to proceed.

Sources

  1. Arizona State University, "Job Order Contracting Performance" (2015 report)
  2. U.S. Army Corps of Engineers, Transatlantic Middle East District, "Old contracting tool leads to new successes in Kuwait"
  3. Army Federal Acquisition Regulation Supplement (AFARS), "Subpart 5117.90 - Job Order Contracts"
  4. Associated Schools of Construction, "Job-Order-Contracting for Facility Owners" (2006)
Next guideJoint scope meetings